A practical kitchen build order

Keep plumbing and wiring accessible until the systems are tested.

The sequence

Finishing the pretty parts too early makes everything behind them harder.

  1. 1Finalize appliances and the cabinet plan.
  2. 2Confirm plumbing and electrical routes.
  3. 3Build the cabinet carcass.
  4. 4Dry-fit the fridge, oven, drawers, and doors.
  5. 5Test every opening and service clearance.
  6. 6Secure the cabinet structure.
  7. 7Route plumbing and electrical while access is open.
  8. 8Fit the countertop and cut the sink opening.
  9. 9Install appliances, drawers, fronts, backsplash, and upper storage.
  10. 10Test water and electrical systems.
  11. 11Load every drawer and test retention.