Installation sequence

1. Freeze the drawing

Complete water-use model, tank/payload check, flow diagram, valve/drain schedule, fitting list and equipment manuals. Mark every service panel.

2. Mount tanks

Install supports, fill, vent, drain, level sensors and wastewater outlets before cabinetry blocks access. Dry-fit the whole system.

3. Supply side

Mount isolation, strainer, pump and accumulator; run cold trunk/manifold; mount heater; run hot branches; add filters and fixtures.

4. Drains and test

Install traps, vents, grey/black plumbing and dump valves. Pressure/leak test before walls, then flush, sanitize, commission and document.

Build rule

If you cannot reach it, isolate it, drain it and explain its pressure/temperature or water-quality job, it is not ready to hide behind a wall.