Chapter 18
Installation sequence
1. Freeze the plan
Complete load sheet, schematic, physical layout, cable/fuse schedule and manuals. Verify components are mutually compatible.
2. Mount dry
Mount enclosures, busbars, disconnects, fuse holders, chargers and inverter on strong surfaces with cooling clearances. Keep batteries disconnected.
3. Route
Run and support large cables first, then branch DC, solar, signals and AC with separation. Protect penetrations before pulling wire.
4. Terminate
Crimp, heat-shrink, label and torque. Install battery last with all fuses removed/open and switches off. Have AC inspected before energizing.
5. Stage power
Commission battery and monitor first, then each charger, DC branch, inverter and AC branch one at a time. Record baseline voltage, current and temperature.
Rule of thumb
If you cannot state the expected current, full conductor length, protection rating and manufacturer limit for a circuit, the circuit is not ready to build.