Commissioning checklist

DoneCheck
All sources isolated before dead tests
Polarity verified at each device
No unintended positive-negative continuity
Battery settings verified
Each source tested alone
Each branch energized separately
High-load thermal test passed
GFCI/RCD and transfer tested
Baseline readings recorded